Planned value

The budgeted cost of the work the baseline scheduled to be complete by a given date. Planned value = budget at completion × planned percent complete.

Planned value answers how much work should have been done by now, expressed in money. The project level formula is the budget at completion multiplied by the planned percent complete, so a £500,000 project scheduled to be 35 percent done at month four has a planned value of £175,000; the rigorous version sums the budgets of the work packages the baseline scheduled to finish by that date. Planned value is a property of the baseline rather than of the plan being worked to this week, so a rebaseline silently changes the meaning of every variance reported before it.

See also

Where this comes up